AWBUD Design & Build, together with Prodlew and Organica signed in November 2007 a contract for the designing and carrying out the modernization of the sewage treatment plant in Piekary ¦l±skie. This task being part of the company environmental protection investments implementation strategy.
Scope of designing and construction works: earthworks, construction of storage reservoir, three warehouses, workshop and warehouse building, two pumping stations and the reconstruction of the administration building. Additionally, modernization of the main pumping station was also performed. The contract was prepared according to the FIDIC rules recommended by the World Bank as applicable to EU structural projects.
Client:
MPWIK Sp. z o.o. Localization:
Piekary ¦l±skie Execution period:
12.2007 – 12.2009 Contract net value:
23 000 000 PLN netto Capacity:
8563 m3/d
Equivalent Number of Inhabitants (ENI):
53342
At the beginning of 2008, AWBUD Design & Build began, as the general contractor, the construction of ecological combined power & heat plant located in Wałcz. The facility will be a landmark in its kind due to technology applied and will provide a 7.2 MW of power production. Synergy of modern technology of charcoal production and generation of electric energy will provide an environmental-friendly character of the investment. Approx. 20 thousand tons/year of straw will be used for production of electric energy.
The scope of works included the demolition of existing buildings and erecting new facilities of the plant. The main facilities include the flue gas desulphurization plant, the coal distillation devices, coal packing, seasoning halls and ventilation & cooling tower with an external water cooling system.
Client:
Ozen Plus Sp. z o .o. Localization:
Wałcz Execution period:
01.2008 – 2010 Contract net value:
100 - 200 mln PLN Surface:
15 000 m2 Cubature:
155 000 m3 Output power:
7.2 MW
Reconstruction and extension of mechanical and biological sewage treatment plant “Bobrek” in Bytom. The consortium will perform works on the most of existing technological facilities, including mechanical cleaning station, pumping station, biological reactor and Imhoff tank. Additionally, scope of works has included reconstruction and construction of a new sewer system sections with pumping stations near Konstytucji St. , Worpie and ¦w. Elżbiety St. in Bytom.
Client:
Bytomskie Przedsiębiorstwo Komunalne Sp. z o.o. Localization:
Bytom Execution period:
04.2009 – 03.2010 Contract net value:
12 160 000 PLN netto Capacity:
750 m3/d
ٱczna długo¶ć sieci kanalizacyjnej:
2 km
AWBUD Design & Build as the leader of the consortium with Synkret, has acquired the contract for the extension of sewage system for residential estate located in Bytom - Miechowice. Scope of works on contract, co-financed by EU funds, include replacement of the existing separate sewage system with combined sewage system. Besides that implementation of the main investment, project include construction of new canals and sanitary drainage channels, pipelines, pumping stations in Olchowa and Dzierżonia with land development, roads and vehicle maneuver areas. There will be also executed the underground rainwater storage reservoir.
Client:
Bytomskie Przedsiębiorstwo Komunalne Sp. z o.o. Localization:
Bytom-Miechowice Execution period:
11.2008-10.2009 Contract net value:
6 250 000 EUR netto Cubature:
155 000 m3 Sewer length:
25 km
Sewage pumping station capacity:
22 l/s
Rainwater pumping station capacity:
104 l/s
In August 2006, Design & Build AWBUD wins a public tender for the construction of sewage treatment plant in Ogrodzieniec. The contract has included the construction of the mechanical and biological treatment plant with capacity of 500 m3/day and land development (landscape architecture, roads and green).
In the near future the expansion of sewage treatment to the capacity of 1000 m3/day is planned. AWBUD has designed and executed, plants complete technological system, the press, lime injection unit, aeration grates, agitators and pumps. It’s worth noting that the execution took place in difficult geological conditions, with need of lowering the ground water by 2 m.
Client:
Gmina Ogrodzieniec Execution period:
08.2006 - 11.2007 Contract net value:
3 300 000 PLN netto Capacity:
500 m3/d
Equivalent Number of Inhabitants (ENI):
8300
AWBUD Design & Build as a leader of the consortium, implementing extension and reconstruction of mechanical and biological sewage treatment plant in Kozienice. Contract on FIDIC rules and regulations includes all construction works for waste treatment plant with maximal capacity of 7 629 m3/d and adapt facility to new law regulations.
Client:
Kozienicka Gospodarka Komunalna Sp. z o.o. Localization:
Kozienice Execution period:
06.2010 - 10.2011 Contract net value:
11 500 000 PLN netto Average capacity:
4500 m3/d
ENI:
47 960
MZEC ¦widnica Sp. z o.o. plant extension with technology line based on gasification of biomass. Design of production and storage hall with surface of 500 m2 and infrastructure for implementation of technology line. Construction works were started in January 2010.
Scope of works: Designing and comprehensive construction works
Client:
MZEC ¦widnica Sp. z o .o. Localization:
¦widnica Execution period:
12.2009 – 07.2010 Contract net value:
< 20 mln PLN netto Surface:
500 m2 Power output:
5 MWt
This engineering structure in general contracting is a example of large scale earth works. The facility with 140 thous. Cu. M., lined with geomembrane and implemented gas intakes was executed in 3 months. Earth works with 100 thous. Cu. m. was implemented in one month.
Client:
UG Zawiercie Localization:
Zawiercie Execution period:
06.2004 - 09.2004 Contract net value:
< 20 mln PLN netto Cubature:
140 000 m3